Material requirements planning: system of linear euqations

The material requirements problem is solved via the solution of a set of linear equations. The gozinto structure can be defined with the graph editor.

Symbols:

i,j index of products
a(i,j) number of units of product i required to produce one unit of the immediate successor product j (value of arc form node i to node j in the gozinto structure)
d(i) external demand for product i
v(i,j) total number of units of product i required to produce one unit of product j
r(i) total requirement of product i

Literature:

- Tempelmeier (1999), Chapter D.1